The Camp Creek Stabilization project is part of a three phase plan to protect the Pleasant Valley neighborhood from flash flooding and erosion.

This phase of the project will make modifications to the Camp Creek channel in Garden of the Gods.  It includes installation of “naturalistic” concrete channel stabilization structures and the shaping of banks.  Vegetation destroyed by the process will be replaced.

Construction Timeline

Aug. 29 through Nov. 30, 2016.

Project Cost

Total Construction Cost:  $1,108,600. The City received an $831,450 matching Emergency Watershed Protection grant in spring 2016 from the Natural Resources Conservation Service for the project. The City’s share is $277,150.